ARA director: First phase of plan short by at least $3.2M
BY GEORGE W. RHODES SUN CHRONICLE STAFF
Friday, October 16, 2009 2:17 AM EDT
ATTLEBORO - In what may have been one of his last official acts for the Attleboro Redevelopment Authority, ARA Executive Director Michael Milanoski said this week that a scaled-back version of the first phase of the downtown revitalization plan is underfunded by at least $3.2 million.
The figure came in a presentation to the ARA board and other city officials.
However, the number could be much higher because two key funding agencies, the Federal Transit Administration and the state's Executive Office of Transportation, are refusing to pay for more work on the project until the city reaches a consensus on the new plan and how to pay for it.
Mayor Kevin Dumas slammed the plan two weeks ago, claiming it was at least $5 million short. He criticized the ARA for failing to get funding commitments, along with the lack of a sound budget for the plan.
The plan was cut back late in the summer at the request of the Federal Transit Administration because of protracted conflict between the ARA and city, rising costs and scarce funds.
Milanoski, who along with three other ARA staffers is to be laid off soon because of a lack of money, told the board that a reduced Phase I has about $6 million available for this fiscal year's $5.7 million budget, as long as the ARA and city agree on how to proceed and get federal approval.
But if the city and ARA don't get that approval, about $3.5 million of that money could be delayed or lost.
Milanoski said there's no funding lined up to pay the 2011 fiscal year cost of Phase I that's budgeted at $3.2 million.
The scaled back plan would include the relocation of Wall Street's intersection with South Main so that it's closer to Mill Street.
It would also include the development of a GATRA bus terminal parallel to the southbound railroad tracks, an access road to the terminal, partial construction of a road parallel to Ten Mile River, demolition of the vacated Automatic Machine Co. buildings, construction of a parking lot where those buildings now stand and relocation of the public works yard to Lamb Street or Pond Street North.
Parts of the original project to be delayed include acquisition of the Reynolds and Markman Co. property, which may be contaminated, acquisition of the former Johnson Fabrication site and the full construction of the riverfront road to Olive Street.
Meanwhile, plans to remove pollutants from Automatic Machine and to go out to bid for demolition were approved by the board.
View Comments » 27 comment(s)
« Hide Comments
s-plumb wrote on Oct 17, 2009 5:58 PM:
Most of all, Id like to know how and why McGovern appeared to take a stand against this city, as he was a sponsor of these lobbying efforts against us. "
doug wrote on Oct 16, 2009 9:16 PM:
kevin h. wrote on Oct 16, 2009 4:04 PM:
s-plumb wrote on Oct 16, 2009 4:00 PM:
If Attleboro ever comes back to life, the square will be just as bad off, if not worse, than before.
It took over 1 1/2 years and a ton of money, for very little functional relief.
I think that's a fairly objective summary. "
ricknkim wrote on Oct 16, 2009 3:21 PM:
s-plumb wrote on Oct 16, 2009 3:12 PM:
How do you spell success? "
s-plumb wrote on Oct 16, 2009 2:49 PM:
ricknkim wrote on Oct 16, 2009 2:43 PM:
s-plumb wrote on Oct 16, 2009 2:42 PM:
s-plumb wrote on Oct 16, 2009 2:38 PM:
Also, I don't think I'm the only one who is critical of the outcome. Imagine if there commuters in Attleboro...but as luck would have it there's been a decline in traffic of about 12%; probably more. "
kevin h. wrote on Oct 16, 2009 2:15 PM:
ricknkim wrote on Oct 16, 2009 2:11 PM:
s-plumb wrote on Oct 16, 2009 12:03 PM:
Now the tune is: Whether out of the pockets of individuals, our or collective pockets, we should just let it go. Good plan. "
common_sense wrote on Oct 16, 2009 11:21 AM:
ricknkim wrote on Oct 16, 2009 11:14 AM:
steves wrote on Oct 16, 2009 9:50 AM:
Now for the $64.00 question at what direct cost to us,not counting the grants and fed money wich I understand is still tax money. with them laying off 5 employees with at least 1 making over 100k, what was their true costs to the city per year? "
s-plumb wrote on Oct 16, 2009 9:32 AM:
BTW: the project is still not complete "
ricknkim wrote on Oct 16, 2009 9:28 AM:
I do think they did a decent job on County Square - traffic flows better, the sidewalks are nice and the square is more appealing to the eye. "
common_sense wrote on Oct 16, 2009 9:18 AM:
attleboro's own wrote on Oct 16, 2009 9:15 AM:
All with zero cost to Attleboro taxpayers. "
common_sense wrote on Oct 16, 2009 9:15 AM:
attlebrockton wrote on Oct 16, 2009 9:03 AM:
The ARA's claim to fame is the Swank building that the gov't refurbished and cleaned & the ARA sold to Cookson. They also reference County Square project ,which as Steve Plumb wiil tell you is no great shakes. Personally I think the greatest accomplishment is the Director's ability to cover up all this bad news for so long. "
steves wrote on Oct 16, 2009 8:35 AM:
What has the ARA actually done for the city as far as completed projects?
This is a genuine question, I haven't heard anything of them except failed or 1/2 done jobs. "
IShouldBeMayor wrote on Oct 16, 2009 8:32 AM:
s-plumb wrote on Oct 16, 2009 8:13 AM:
The $3-$4M debt was an estimate from over a year ago of just the IBP; and that with limited information. This was always thought to be conservative. Add lawsuits of several million dollars, interest and penatlties on loans, as well as daily operating overhead, and we're probably looking at $6M-$7M. "
do you get it? wrote on Oct 16, 2009 8:08 AM:
kevin h. wrote on Oct 16, 2009 7:58 AM:
- $5 Million.....Downtown
- $3-4 Million...IBP
__________________________
- $8-9 Million total ARA fup.
JUST STOP IT!!
When you are in a hole, stop digging! "